<?xml version="1.0" encoding="UTF-8" standalone="yes"?>
<Project xmlns="http://schemas.microsoft.com/project">
    <Name>IBM Tivoli Identity Manager Project</Name>
    <Title>IBM Tivoli Identity Manager Project</Title>
    <Manager/>
    <ScheduleFromStart>1</ScheduleFromStart>
    <StartDate>2010-01-01T17:00:00</StartDate>
    <FinishDate>2010-01-01T17:00:00</FinishDate>
    <FYStartDate>1</FYStartDate>
    <CriticalSlackLimit>0</CriticalSlackLimit>
    <CurrencyDigits>2</CurrencyDigits>
    <CurrencySymbol>$</CurrencySymbol>
    <CurrencySymbolPosition>0</CurrencySymbolPosition>
    <CalendarUID>1</CalendarUID>
    <DefaultStartTime>09:00:00</DefaultStartTime>
    <DefaultFinishTime>18:00:00</DefaultFinishTime>
    <MinutesPerDay>480</MinutesPerDay>
    <MinutesPerWeek>2400</MinutesPerWeek>
    <DaysPerMonth>20</DaysPerMonth>
    <DefaultTaskType>0</DefaultTaskType>
    <DefaultFixedCostAccrual>2</DefaultFixedCostAccrual>
    <DefaultStandardRate>10</DefaultStandardRate>
    <DefaultOvertimeRate>15</DefaultOvertimeRate>
    <DurationFormat>7</DurationFormat>
    <WorkFormat>2</WorkFormat>
    <EditableActualCosts>0</EditableActualCosts>
    <HonorConstraints>0</HonorConstraints>
    <EarnedValueMethod>0</EarnedValueMethod>
    <InsertedProjectsLikeSummary>0</InsertedProjectsLikeSummary>
    <MultipleCriticalPaths>0</MultipleCriticalPaths>
    <NewTasksEffortDriven>0</NewTasksEffortDriven>
    <NewTasksEstimated>1</NewTasksEstimated>
    <SplitsInProgressTasks>0</SplitsInProgressTasks>
    <SpreadActualCost>0</SpreadActualCost>
    <SpreadPercentComplete>0</SpreadPercentComplete>
    <TaskUpdatesResource>1</TaskUpdatesResource>
    <FiscalYearStart>0</FiscalYearStart>
    <WeekStartDay>1</WeekStartDay>
    <MoveCompletedEndsBack>0</MoveCompletedEndsBack>
    <MoveRemainingStartsBack>0</MoveRemainingStartsBack>
    <MoveRemainingStartsForward>0</MoveRemainingStartsForward>
    <MoveCompletedEndsForward>0</MoveCompletedEndsForward>
    <BaselineForEarnedValue>0</BaselineForEarnedValue>
    <AutoAddNewResourcesAndTasks>1</AutoAddNewResourcesAndTasks>
    <CurrentDate>2010-06-28T17:41:00</CurrentDate>
    <MicrosoftProjectServerURL>1</MicrosoftProjectServerURL>
    <Autolink>1</Autolink>
    <NewTaskStartDate>0</NewTaskStartDate>
    <DefaultTaskEVMethod>0</DefaultTaskEVMethod>
    <ProjectExternallyEdited>0</ProjectExternallyEdited>
    <ActualsInSync>0</ActualsInSync>
    <RemoveFileProperties>0</RemoveFileProperties>
    <AdminProject>0</AdminProject>
    <ExtendedAttributes>
        <ExtendedAttribute>
            <FieldID>188743731</FieldID>
            <FieldName>Text1</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743734</FieldID>
            <FieldName>Text2</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743737</FieldID>
            <FieldName>Text3</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743740</FieldID>
            <FieldName>Text4</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743743</FieldID>
            <FieldName>Text5</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743746</FieldID>
            <FieldName>Text6</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743747</FieldID>
            <FieldName>Text7</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743748</FieldID>
            <FieldName>Text8</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743749</FieldID>
            <FieldName>Text9</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743750</FieldID>
            <FieldName>Text10</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743997</FieldID>
            <FieldName>Text11</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743998</FieldID>
            <FieldName>Text12</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743999</FieldID>
            <FieldName>Text13</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744000</FieldID>
            <FieldName>Text14</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744001</FieldID>
            <FieldName>Text15</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744002</FieldID>
            <FieldName>Text16</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744003</FieldID>
            <FieldName>Text17</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744004</FieldID>
            <FieldName>Text18</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744005</FieldID>
            <FieldName>Text19</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744006</FieldID>
            <FieldName>Text20</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744007</FieldID>
            <FieldName>Text21</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744008</FieldID>
            <FieldName>Text22</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744009</FieldID>
            <FieldName>Text23</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744010</FieldID>
            <FieldName>Text24</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744011</FieldID>
            <FieldName>Text25</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744012</FieldID>
            <FieldName>Text26</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744013</FieldID>
            <FieldName>Text27</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744014</FieldID>
            <FieldName>Text28</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744015</FieldID>
            <FieldName>Text29</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744016</FieldID>
            <FieldName>Text30</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743732</FieldID>
            <FieldName>Start1</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743735</FieldID>
            <FieldName>Start2</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743738</FieldID>
            <FieldName>Start3</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743741</FieldID>
            <FieldName>Start4</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743744</FieldID>
            <FieldName>Start5</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743962</FieldID>
            <FieldName>Start6</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743964</FieldID>
            <FieldName>Start7</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743966</FieldID>
            <FieldName>Start8</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743968</FieldID>
            <FieldName>Start9</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743970</FieldID>
            <FieldName>Start10</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743733</FieldID>
            <FieldName>Finish1</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743736</FieldID>
            <FieldName>Finish2</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743739</FieldID>
            <FieldName>Finish3</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743742</FieldID>
            <FieldName>Finish4</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743745</FieldID>
            <FieldName>Finish5</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743963</FieldID>
            <FieldName>Finish6</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743965</FieldID>
            <FieldName>Finish7</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743967</FieldID>
            <FieldName>Finish8</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743969</FieldID>
            <FieldName>Finish9</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743971</FieldID>
            <FieldName>Finish10</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743786</FieldID>
            <FieldName>Cost1</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743787</FieldID>
            <FieldName>Cost2</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743788</FieldID>
            <FieldName>Cost3</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743938</FieldID>
            <FieldName>Cost4</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743939</FieldID>
            <FieldName>Cost5</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743940</FieldID>
            <FieldName>Cost6</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743941</FieldID>
            <FieldName>Cost7</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743942</FieldID>
            <FieldName>Cost8</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743943</FieldID>
            <FieldName>Cost9</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743944</FieldID>
            <FieldName>Cost10</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743945</FieldID>
            <FieldName>Date1</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743946</FieldID>
            <FieldName>Date2</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743947</FieldID>
            <FieldName>Date3</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743948</FieldID>
            <FieldName>Date4</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743949</FieldID>
            <FieldName>Date5</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743950</FieldID>
            <FieldName>Date6</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743951</FieldID>
            <FieldName>Date7</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743952</FieldID>
            <FieldName>Date8</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743953</FieldID>
            <FieldName>Date9</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743954</FieldID>
            <FieldName>Date10</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743752</FieldID>
            <FieldName>Flag1</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743753</FieldID>
            <FieldName>Flag2</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743754</FieldID>
            <FieldName>Flag3</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743755</FieldID>
            <FieldName>Flag4</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743756</FieldID>
            <FieldName>Flag5</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743757</FieldID>
            <FieldName>Flag6</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743758</FieldID>
            <FieldName>Flag7</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743759</FieldID>
            <FieldName>Flag8</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743760</FieldID>
            <FieldName>Flag9</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743761</FieldID>
            <FieldName>Flag10</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743972</FieldID>
            <FieldName>Flag11</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743973</FieldID>
            <FieldName>Flag12</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743974</FieldID>
            <FieldName>Flag13</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743975</FieldID>
            <FieldName>Flag14</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743976</FieldID>
            <FieldName>Flag15</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743977</FieldID>
            <FieldName>Flag16</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743978</FieldID>
            <FieldName>Flag17</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743979</FieldID>
            <FieldName>Flag18</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743980</FieldID>
            <FieldName>Flag19</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743981</FieldID>
            <FieldName>Flag20</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743767</FieldID>
            <FieldName>Number1</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743768</FieldID>
            <FieldName>Number2</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743769</FieldID>
            <FieldName>Number3</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743770</FieldID>
            <FieldName>Number4</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743771</FieldID>
            <FieldName>Number5</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743982</FieldID>
            <FieldName>Number6</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743983</FieldID>
            <FieldName>Number7</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743984</FieldID>
            <FieldName>Number8</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743985</FieldID>
            <FieldName>Number9</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743986</FieldID>
            <FieldName>Number10</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743987</FieldID>
            <FieldName>Number11</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743988</FieldID>
            <FieldName>Number12</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743989</FieldID>
            <FieldName>Number13</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743990</FieldID>
            <FieldName>Number14</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743991</FieldID>
            <FieldName>Number15</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743992</FieldID>
            <FieldName>Number16</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743993</FieldID>
            <FieldName>Number17</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743994</FieldID>
            <FieldName>Number18</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743995</FieldID>
            <FieldName>Number19</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743996</FieldID>
            <FieldName>Number20</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743783</FieldID>
            <FieldName>Duration1</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743784</FieldID>
            <FieldName>Duration2</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743785</FieldID>
            <FieldName>Duration3</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743955</FieldID>
            <FieldName>Duration4</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743956</FieldID>
            <FieldName>Duration5</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743957</FieldID>
            <FieldName>Duration6</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743958</FieldID>
            <FieldName>Duration7</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743959</FieldID>
            <FieldName>Duration8</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743960</FieldID>
            <FieldName>Duration9</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188743961</FieldID>
            <FieldName>Duration10</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744096</FieldID>
            <FieldName>Outline Code1</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744098</FieldID>
            <FieldName>Outline Code2</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744100</FieldID>
            <FieldName>Outline Code3</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744102</FieldID>
            <FieldName>Outline Code4</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744104</FieldID>
            <FieldName>Outline Code5</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744106</FieldID>
            <FieldName>Outline Code6</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744108</FieldID>
            <FieldName>Outline Code7</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744110</FieldID>
            <FieldName>Outline Code8</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744112</FieldID>
            <FieldName>Outline Code9</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>188744114</FieldID>
            <FieldName>Outline Code10</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205520904</FieldID>
            <FieldName>Text1</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205520905</FieldID>
            <FieldName>Text2</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205520926</FieldID>
            <FieldName>Text3</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205520927</FieldID>
            <FieldName>Text4</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205520928</FieldID>
            <FieldName>Text5</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205520993</FieldID>
            <FieldName>Text6</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205520994</FieldID>
            <FieldName>Text7</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205520995</FieldID>
            <FieldName>Text8</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205520996</FieldID>
            <FieldName>Text9</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205520997</FieldID>
            <FieldName>Text10</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521121</FieldID>
            <FieldName>Text11</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521122</FieldID>
            <FieldName>Text12</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521123</FieldID>
            <FieldName>Text13</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521124</FieldID>
            <FieldName>Text14</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521125</FieldID>
            <FieldName>Text15</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521126</FieldID>
            <FieldName>Text16</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521127</FieldID>
            <FieldName>Text17</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521128</FieldID>
            <FieldName>Text18</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521129</FieldID>
            <FieldName>Text19</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521130</FieldID>
            <FieldName>Text20</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521131</FieldID>
            <FieldName>Text21</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521132</FieldID>
            <FieldName>Text22</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521133</FieldID>
            <FieldName>Text23</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521134</FieldID>
            <FieldName>Text24</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521135</FieldID>
            <FieldName>Text25</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521136</FieldID>
            <FieldName>Text26</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521137</FieldID>
            <FieldName>Text27</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521138</FieldID>
            <FieldName>Text28</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521139</FieldID>
            <FieldName>Text29</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521140</FieldID>
            <FieldName>Text30</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205520998</FieldID>
            <FieldName>Start1</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205520999</FieldID>
            <FieldName>Start2</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521000</FieldID>
            <FieldName>Start3</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521001</FieldID>
            <FieldName>Start4</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521002</FieldID>
            <FieldName>Start5</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521116</FieldID>
            <FieldName>Start6</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521117</FieldID>
            <FieldName>Start7</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521118</FieldID>
            <FieldName>Start8</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521119</FieldID>
            <FieldName>Start9</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521120</FieldID>
            <FieldName>Start10</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521003</FieldID>
            <FieldName>Finish1</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521004</FieldID>
            <FieldName>Finish2</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521005</FieldID>
            <FieldName>Finish3</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521006</FieldID>
            <FieldName>Finish4</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521007</FieldID>
            <FieldName>Finish5</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521086</FieldID>
            <FieldName>Finish6</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521087</FieldID>
            <FieldName>Finish7</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521088</FieldID>
            <FieldName>Finish8</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521089</FieldID>
            <FieldName>Finish9</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521090</FieldID>
            <FieldName>Finish10</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521019</FieldID>
            <FieldName>Cost1</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521020</FieldID>
            <FieldName>Cost2</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521021</FieldID>
            <FieldName>Cost3</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521062</FieldID>
            <FieldName>Cost4</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521063</FieldID>
            <FieldName>Cost5</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521064</FieldID>
            <FieldName>Cost6</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521065</FieldID>
            <FieldName>Cost7</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521066</FieldID>
            <FieldName>Cost8</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521067</FieldID>
            <FieldName>Cost9</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521068</FieldID>
            <FieldName>Cost10</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521069</FieldID>
            <FieldName>Date1</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521070</FieldID>
            <FieldName>Date2</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521071</FieldID>
            <FieldName>Date3</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521072</FieldID>
            <FieldName>Date4</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521073</FieldID>
            <FieldName>Date5</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521074</FieldID>
            <FieldName>Date6</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521075</FieldID>
            <FieldName>Date7</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521076</FieldID>
            <FieldName>Date8</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521077</FieldID>
            <FieldName>Date9</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521078</FieldID>
            <FieldName>Date10</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521023</FieldID>
            <FieldName>Flag1</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521024</FieldID>
            <FieldName>Flag2</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521025</FieldID>
            <FieldName>Flag3</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521026</FieldID>
            <FieldName>Flag4</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521027</FieldID>
            <FieldName>Flag5</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521028</FieldID>
            <FieldName>Flag6</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521029</FieldID>
            <FieldName>Flag7</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521030</FieldID>
            <FieldName>Flag8</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521031</FieldID>
            <FieldName>Flag9</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521022</FieldID>
            <FieldName>Flag10</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521091</FieldID>
            <FieldName>Flag11</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521092</FieldID>
            <FieldName>Flag12</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521093</FieldID>
            <FieldName>Flag13</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521094</FieldID>
            <FieldName>Flag14</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521095</FieldID>
            <FieldName>Flag15</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521096</FieldID>
            <FieldName>Flag16</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521097</FieldID>
            <FieldName>Flag17</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521098</FieldID>
            <FieldName>Flag18</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521099</FieldID>
            <FieldName>Flag19</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521100</FieldID>
            <FieldName>Flag20</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521008</FieldID>
            <FieldName>Number1</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521009</FieldID>
            <FieldName>Number2</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521010</FieldID>
            <FieldName>Number3</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521011</FieldID>
            <FieldName>Number4</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521012</FieldID>
            <FieldName>Number5</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521101</FieldID>
            <FieldName>Number6</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521102</FieldID>
            <FieldName>Number7</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521103</FieldID>
            <FieldName>Number8</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521104</FieldID>
            <FieldName>Number9</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521105</FieldID>
            <FieldName>Number10</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521106</FieldID>
            <FieldName>Number11</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521107</FieldID>
            <FieldName>Number12</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521108</FieldID>
            <FieldName>Number13</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521109</FieldID>
            <FieldName>Number14</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521110</FieldID>
            <FieldName>Number15</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521111</FieldID>
            <FieldName>Number16</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521112</FieldID>
            <FieldName>Number17</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521113</FieldID>
            <FieldName>Number18</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521114</FieldID>
            <FieldName>Number19</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521115</FieldID>
            <FieldName>Number20</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521013</FieldID>
            <FieldName>Duration1</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521014</FieldID>
            <FieldName>Duration2</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521015</FieldID>
            <FieldName>Duration3</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521079</FieldID>
            <FieldName>Duration4</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521080</FieldID>
            <FieldName>Duration5</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521081</FieldID>
            <FieldName>Duration6</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521082</FieldID>
            <FieldName>Duration7</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521083</FieldID>
            <FieldName>Duration8</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521084</FieldID>
            <FieldName>Duration9</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521085</FieldID>
            <FieldName>Duration10</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521174</FieldID>
            <FieldName>Outline Code1</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521176</FieldID>
            <FieldName>Outline Code2</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521178</FieldID>
            <FieldName>Outline Code3</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521180</FieldID>
            <FieldName>Outline Code4</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521182</FieldID>
            <FieldName>Outline Code5</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521184</FieldID>
            <FieldName>Outline Code6</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521186</FieldID>
            <FieldName>Outline Code7</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521188</FieldID>
            <FieldName>Outline Code8</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521190</FieldID>
            <FieldName>Outline Code9</FieldName>
        </ExtendedAttribute>
        <ExtendedAttribute>
            <FieldID>205521192</FieldID>
            <FieldName>Outline Code10</FieldName>
        </ExtendedAttribute>
    </ExtendedAttributes>
    <Calendars>
        <Calendar>
            <UID>1</UID>
            <Name>Standard</Name>
            <IsBaseCalendar>1</IsBaseCalendar>
            <WeekDays>
                <WeekDay>
                    <DayType>1</DayType>
                    <DayWorking>0</DayWorking>
                </WeekDay>
                <WeekDay>
                    <DayType>2</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>08:00:00</FromTime>
                            <ToTime>12:00:00</ToTime>
                        </WorkingTime>
                        <WorkingTime>
                            <FromTime>13:00:00</FromTime>
                            <ToTime>17:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
                <WeekDay>
                    <DayType>3</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>08:00:00</FromTime>
                            <ToTime>12:00:00</ToTime>
                        </WorkingTime>
                        <WorkingTime>
                            <FromTime>13:00:00</FromTime>
                            <ToTime>17:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
                <WeekDay>
                    <DayType>4</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>08:00:00</FromTime>
                            <ToTime>12:00:00</ToTime>
                        </WorkingTime>
                        <WorkingTime>
                            <FromTime>13:00:00</FromTime>
                            <ToTime>17:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
                <WeekDay>
                    <DayType>5</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>08:00:00</FromTime>
                            <ToTime>12:00:00</ToTime>
                        </WorkingTime>
                        <WorkingTime>
                            <FromTime>13:00:00</FromTime>
                            <ToTime>17:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
                <WeekDay>
                    <DayType>6</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>08:00:00</FromTime>
                            <ToTime>12:00:00</ToTime>
                        </WorkingTime>
                        <WorkingTime>
                            <FromTime>13:00:00</FromTime>
                            <ToTime>17:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
                <WeekDay>
                    <DayType>7</DayType>
                    <DayWorking>0</DayWorking>
                </WeekDay>
            </WeekDays>
        </Calendar>
        <Calendar>
            <UID>2</UID>
            <Name>24 Hours</Name>
            <IsBaseCalendar>1</IsBaseCalendar>
            <WeekDays>
                <WeekDay>
                    <DayType>1</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>00:00:00</FromTime>
                            <ToTime>00:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
                <WeekDay>
                    <DayType>2</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>00:00:00</FromTime>
                            <ToTime>00:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
                <WeekDay>
                    <DayType>3</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>00:00:00</FromTime>
                            <ToTime>00:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
                <WeekDay>
                    <DayType>4</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>00:00:00</FromTime>
                            <ToTime>00:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
                <WeekDay>
                    <DayType>5</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>00:00:00</FromTime>
                            <ToTime>00:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
                <WeekDay>
                    <DayType>6</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>00:00:00</FromTime>
                            <ToTime>00:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
                <WeekDay>
                    <DayType>7</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>00:00:00</FromTime>
                            <ToTime>00:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
            </WeekDays>
        </Calendar>
        <Calendar>
            <UID>3</UID>
            <Name>Night Shift</Name>
            <IsBaseCalendar>1</IsBaseCalendar>
            <WeekDays>
                <WeekDay>
                    <DayType>1</DayType>
                    <DayWorking>0</DayWorking>
                </WeekDay>
                <WeekDay>
                    <DayType>2</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>23:00:00</FromTime>
                            <ToTime>00:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
                <WeekDay>
                    <DayType>3</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>00:00:00</FromTime>
                            <ToTime>03:00:00</ToTime>
                        </WorkingTime>
                        <WorkingTime>
                            <FromTime>04:00:00</FromTime>
                            <ToTime>08:00:00</ToTime>
                        </WorkingTime>
                        <WorkingTime>
                            <FromTime>23:00:00</FromTime>
                            <ToTime>00:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
                <WeekDay>
                    <DayType>4</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>00:00:00</FromTime>
                            <ToTime>03:00:00</ToTime>
                        </WorkingTime>
                        <WorkingTime>
                            <FromTime>04:00:00</FromTime>
                            <ToTime>08:00:00</ToTime>
                        </WorkingTime>
                        <WorkingTime>
                            <FromTime>23:00:00</FromTime>
                            <ToTime>00:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
                <WeekDay>
                    <DayType>5</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>00:00:00</FromTime>
                            <ToTime>03:00:00</ToTime>
                        </WorkingTime>
                        <WorkingTime>
                            <FromTime>04:00:00</FromTime>
                            <ToTime>08:00:00</ToTime>
                        </WorkingTime>
                        <WorkingTime>
                            <FromTime>23:00:00</FromTime>
                            <ToTime>00:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
                <WeekDay>
                    <DayType>6</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>00:00:00</FromTime>
                            <ToTime>03:00:00</ToTime>
                        </WorkingTime>
                        <WorkingTime>
                            <FromTime>04:00:00</FromTime>
                            <ToTime>08:00:00</ToTime>
                        </WorkingTime>
                        <WorkingTime>
                            <FromTime>23:00:00</FromTime>
                            <ToTime>00:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
                <WeekDay>
                    <DayType>7</DayType>
                    <DayWorking>1</DayWorking>
                    <WorkingTimes>
                        <WorkingTime>
                            <FromTime>00:00:00</FromTime>
                            <ToTime>03:00:00</ToTime>
                        </WorkingTime>
                        <WorkingTime>
                            <FromTime>04:00:00</FromTime>
                            <ToTime>08:00:00</ToTime>
                        </WorkingTime>
                    </WorkingTimes>
                </WeekDay>
            </WeekDays>
        </Calendar>
        <Calendar>
            <UID>4</UID>
            <Name>PM</Name>
            <IsBaseCalendar>0</IsBaseCalendar>
            <BaseCalendarUID>1</BaseCalendarUID>
            <WeekDays/>
        </Calendar>
        <Calendar>
            <UID>5</UID>
            <Name>Admin</Name>
            <IsBaseCalendar>0</IsBaseCalendar>
            <BaseCalendarUID>1</BaseCalendarUID>
            <WeekDays/>
        </Calendar>
        <Calendar>
            <UID>6</UID>
            <Name>TCons</Name>
            <IsBaseCalendar>0</IsBaseCalendar>
            <BaseCalendarUID>1</BaseCalendarUID>
            <WeekDays/>
        </Calendar>
        <Calendar>
            <UID>7</UID>
            <Name>Eng</Name>
            <IsBaseCalendar>0</IsBaseCalendar>
            <BaseCalendarUID>1</BaseCalendarUID>
            <WeekDays/>
        </Calendar>
        <Calendar>
            <UID>8</UID>
            <Name>C-PM</Name>
            <IsBaseCalendar>0</IsBaseCalendar>
            <BaseCalendarUID>1</BaseCalendarUID>
            <WeekDays/>
        </Calendar>
        <Calendar>
            <UID>9</UID>
            <Name>C-Tech</Name>
            <IsBaseCalendar>0</IsBaseCalendar>
            <BaseCalendarUID>1</BaseCalendarUID>
            <WeekDays/>
        </Calendar>
    </Calendars>
    <Tasks>
        <Task>
            <UID>1</UID>
            <ID>1</ID>
            <Name>Pre-implementation</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:29:00</CreateDate>
            <WBS/>
            <OutlineNumber>1</OutlineNumber>
            <OutlineLevel>1</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-11-20T15:40:00</Start>
            <Finish>2009-12-04T17:00:00</Finish>
            <Duration>PT81H20M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14880000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT81H20M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>2</UID>
            <ID>2</ID>
            <Name>Analyze and verify project goals</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:29:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.1</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-11-20T15:40:00</Start>
            <Finish>2009-11-27T10:40:00</Finish>
            <Duration>PT36H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14480000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT36H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>3</UID>
            <ID>3</ID>
            <Name>Review and recap proposals and contracts</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:30:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.1.1</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-11-20T15:40:00</Start>
            <Finish>2009-11-23T15:40:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14480000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>4</UID>
            <ID>4</ID>
            <Name>Assess project opportunities and risks</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:31:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.1.2</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-11-23T15:40:00</Start>
            <Finish>2009-11-24T15:40:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14480000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>3</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>5</UID>
            <ID>5</ID>
            <Name>Identify constraints and extraordinary obstacles</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:31:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.1.3</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-11-23T15:40:00</Start>
            <Finish>2009-11-24T15:40:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14480000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>3</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>6</UID>
            <ID>6</ID>
            <Name>Identify requisite nonhuman resources</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:31:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.1.4</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-11-23T15:40:00</Start>
            <Finish>2009-11-24T15:40:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14480000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>3</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>7</UID>
            <ID>7</ID>
            <Name>Review scope with the project manager</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:31:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.1.5</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-11-24T15:40:00</Start>
            <Finish>2009-11-25T10:40:00</Finish>
            <Duration>PT4H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14480000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT4H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>3</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <PredecessorLink>
                <PredecessorUID>4</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <PredecessorLink>
                <PredecessorUID>5</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <PredecessorLink>
                <PredecessorUID>6</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>8</UID>
            <ID>8</ID>
            <Name>Identify the success criteria</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:31:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.1.6</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-11-25T10:40:00</Start>
            <Finish>2009-11-26T10:40:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14480000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>7</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>9</UID>
            <ID>9</ID>
            <Name>Project high-level scope set</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:31:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.1.7</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-11-26T10:40:00</Start>
            <Finish>2009-11-27T10:40:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14480000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>8</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>10</UID>
            <ID>10</ID>
            <Name>Assemble core project team</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:31:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.2</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-11-27T10:40:00</Start>
            <Finish>2009-12-01T17:00:00</Finish>
            <Duration>PT21H20M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14480000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT21H20M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>2</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>11</UID>
            <ID>11</ID>
            <Name>Identify needed skills from IBM</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:31:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.2.1</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-11-27T10:40:00</Start>
            <Finish>2009-11-30T10:40:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14480000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>12</UID>
            <ID>12</ID>
            <Name>Identify needed skills from organization</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:31:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.2.2</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-11-27T15:40:00</Start>
            <Finish>2009-11-30T10:40:00</Finish>
            <Duration>PT4H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14240000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT4H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>13</UID>
            <ID>13</ID>
            <Name>Analyze staff availability</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:31:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.2.3</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-11-30T10:40:00</Start>
            <Finish>2009-11-30T15:40:00</Finish>
            <Duration>PT4H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14480000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT4H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>11</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <PredecessorLink>
                <PredecessorUID>12</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>14</UID>
            <ID>14</ID>
            <Name>Nominate prospective members</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:31:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.2.4</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-11-30T15:40:00</Start>
            <Finish>2009-12-01T15:40:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14480000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>13</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>15</UID>
            <ID>15</ID>
            <Name>Review team’s availability</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:31:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.2.5</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-01T12:00:00</Start>
            <Finish>2009-12-01T17:00:00</Finish>
            <Duration>PT4H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13440000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT4H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>7</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>16</UID>
            <ID>16</ID>
            <Name>Team members accept assignment</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:31:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.2.6</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-01T15:40:00</Start>
            <Finish>2009-12-01T17:00:00</Finish>
            <Duration>PT1H20M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14480000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT1H20M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>14</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>17</UID>
            <ID>17</ID>
            <Name>Establish project goals</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:31:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.3</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-02T08:00:00</Start>
            <Finish>2009-12-02T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14880000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>18</UID>
            <ID>18</ID>
            <Name>Review project goals and plans with team members</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:32:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.3.1</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-02T08:00:00</Start>
            <Finish>2009-12-02T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14880000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>10</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>19</UID>
            <ID>19</ID>
            <Name>Develop project plan with resources identified</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:32:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.3.2</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-02T08:00:00</Start>
            <Finish>2009-12-02T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14880000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>2</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <PredecessorLink>
                <PredecessorUID>10</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>20</UID>
            <ID>20</ID>
            <Name>Design test strategy</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:32:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.3.3</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-02T12:00:00</Start>
            <Finish>2009-12-02T17:00:00</Finish>
            <Duration>PT4H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-12960000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT4H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>2</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>21</UID>
            <ID>21</ID>
            <Name>Project communications</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:32:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.4</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-03T08:00:00</Start>
            <Finish>2009-12-03T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14400000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>10</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>22</UID>
            <ID>22</ID>
            <Name>Publish communications plan</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:32:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.4.1</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-03T08:00:00</Start>
            <Finish>2009-12-03T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14400000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>23</UID>
            <ID>23</ID>
            <Name>Identify and publish status update schedule</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:32:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.4.2</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-03T08:00:00</Start>
            <Finish>2009-12-03T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14400000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>24</UID>
            <ID>24</ID>
            <Name>Publish problem and issue tracking instructions</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:32:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.4.3</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-03T08:00:00</Start>
            <Finish>2009-12-03T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14400000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>25</UID>
            <ID>25</ID>
            <Name>Publish change control instructions</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:32:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.4.4</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-03T08:00:00</Start>
            <Finish>2009-12-03T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14400000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>26</UID>
            <ID>26</ID>
            <Name>Publish team schedules</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:32:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.4.5</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-03T08:00:00</Start>
            <Finish>2009-12-03T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14400000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>27</UID>
            <ID>27</ID>
            <Name>Publish team status reporting rules</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:32:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.4.6</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-03T08:00:00</Start>
            <Finish>2009-12-03T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14400000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>28</UID>
            <ID>28</ID>
            <Name>Publish Tivoli Identity Manager and expense reporting rules</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:32:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.4.7</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-03T08:00:00</Start>
            <Finish>2009-12-03T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14400000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>29</UID>
            <ID>29</ID>
            <Name>Identify and publish position functional responsibilities</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:32:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.4.8</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-03T08:00:00</Start>
            <Finish>2009-12-03T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14400000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>16</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>30</UID>
            <ID>30</ID>
            <Name>Project kick-off</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:32:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.5</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-03T08:00:00</Start>
            <Finish>2009-12-03T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14880000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>2</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <PredecessorLink>
                <PredecessorUID>10</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <PredecessorLink>
                <PredecessorUID>17</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>31</UID>
            <ID>31</ID>
            <Name>Confirm work space suitability</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:33:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.5.1</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-03T12:00:00</Start>
            <Finish>2009-12-03T17:00:00</Finish>
            <Duration>PT4H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14880000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT4H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>34</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>32</UID>
            <ID>32</ID>
            <Name>Confirm IBM and organization teams are in place</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:33:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.5.2</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-03T12:00:00</Start>
            <Finish>2009-12-03T17:00:00</Finish>
            <Duration>PT4H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14880000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT4H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>34</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>33</UID>
            <ID>33</ID>
            <Name>Confirm resources are suitable and in place</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:33:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.5.3</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-03T12:00:00</Start>
            <Finish>2009-12-03T17:00:00</Finish>
            <Duration>PT4H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14880000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT4H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>34</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>34</UID>
            <ID>34</ID>
            <Name>Conduct kick-off meeting</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:33:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.5.4</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-03T08:00:00</Start>
            <Finish>2009-12-03T12:00:00</Finish>
            <Duration>PT4H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14880000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT4H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>35</UID>
            <ID>35</ID>
            <Name>Project preliminaries in place</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:33:00</CreateDate>
            <WBS/>
            <OutlineNumber>1.6</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-04T08:00:00</Start>
            <Finish>2009-12-04T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14880000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>2</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <PredecessorLink>
                <PredecessorUID>10</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <PredecessorLink>
                <PredecessorUID>21</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <PredecessorLink>
                <PredecessorUID>30</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>37</UID>
            <ID>37</ID>
            <Name>Implementation</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:33:00</CreateDate>
            <WBS/>
            <OutlineNumber>2</OutlineNumber>
            <OutlineLevel>1</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-07T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT160H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-8400000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT160H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>35</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>38</UID>
            <ID>38</ID>
            <Name>Design and analysis</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:33:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.1</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5760000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>39</UID>
            <ID>39</ID>
            <Name>Analyze and design organizational units</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:34:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.1.1</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T12:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT4H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5520000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT4H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>40</UID>
            <ID>40</ID>
            <Name>Analyze and design organizational roles</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:34:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.1.2</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5760000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>41</UID>
            <ID>41</ID>
            <Name>Analyze and design provisioning policies and workflows</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:34:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.1.3</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5760000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>42</UID>
            <ID>42</ID>
            <Name>Analyze and design Tivoli Identity Manager security (ACIs and ITIM groups)</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:34:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.1.4</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5760000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>43</UID>
            <ID>43</ID>
            <Name>Analyze and design password policies</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:34:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.1.5</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5760000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>44</UID>
            <ID>44</ID>
            <Name>Analyze and design identity policies</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:34:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.1.6</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5760000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>45</UID>
            <ID>45</ID>
            <Name>Analyze and design high level data import methods</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:34:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.1.7</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5760000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>46</UID>
            <ID>46</ID>
            <Name>Document hardware and software architecture</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:34:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.1.8</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5760000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>47</UID>
            <ID>47</ID>
            <Name>Set up development and test environments</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:34:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-07T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT160H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-8400000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT160H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>48</UID>
            <ID>48</ID>
            <Name>Identify and set up hardware</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:34:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.1</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5760000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>49</UID>
            <ID>49</ID>
            <Name>Configure hardware</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:35:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.1.1</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5760000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>50</UID>
            <ID>50</ID>
            <Name>Verify system size requirements</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:35:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.1.2</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5760000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>51</UID>
            <ID>51</ID>
            <Name>Establish interconnect to network</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:35:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.1.3</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5760000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>52</UID>
            <ID>52</ID>
            <Name>Produce hardware and software architecture diagram</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:35:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.1.4</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5760000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>53</UID>
            <ID>53</ID>
            <Name>Review Architecture with client</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:35:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.1.5</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5760000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>54</UID>
            <ID>54</ID>
            <Name>Install software</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T17:15:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.2</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5760000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>55</UID>
            <ID>55</ID>
            <Name>Install or validate operating systems and patches</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T17:15:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.2.1</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5760000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>56</UID>
            <ID>56</ID>
            <Name>Install or validate database engine and patches</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T17:15:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.2.2</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5760000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>57</UID>
            <ID>57</ID>
            <Name>Install or validate Web proxy</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T17:15:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.2.3</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5760000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>58</UID>
            <ID>58</ID>
            <Name>Install or validate directory server</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T17:15:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.2.4</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5760000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>59</UID>
            <ID>59</ID>
            <Name>Install Tivoli Identity Manager systems</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:37:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-29T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT32H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7200000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT32H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>60</UID>
            <ID>60</ID>
            <Name>Install Tivoli Identity Manager server</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:38:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.1</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5760000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>61</UID>
            <ID>61</ID>
            <Name>E-mail notification installation and configuration</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:38:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.2</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-29T08:00:00</Start>
            <Finish>2009-12-29T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7200000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>62</UID>
            <ID>62</ID>
            <Name>Install or configure SMTP on the server</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:38:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.2.1</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-29T08:00:00</Start>
            <Finish>2009-12-29T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7200000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>63</UID>
            <ID>63</ID>
            <Name>Install adapters</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:38:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.3</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-30T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT24H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7200000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT24H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>61</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>64</UID>
            <ID>64</ID>
            <Name>Adapter 1</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:38:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.3.1</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-30T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT24H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7200000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT24H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>65</UID>
            <ID>65</ID>
            <Name>Install adapter 1</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:38:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.3.1.1</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-30T08:00:00</Start>
            <Finish>2009-12-30T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7200000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>66</UID>
            <ID>66</ID>
            <Name>Configure adapter 1</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:38:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.3.1.2</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-31T08:00:00</Start>
            <Finish>2009-12-31T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7200000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>65</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>67</UID>
            <ID>67</ID>
            <Name>Review and approve adapter 1 installation</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:38:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.3.1.3</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7200000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>66</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>68</UID>
            <ID>68</ID>
            <Name>Adapter 2</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:38:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.3.2</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-30T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT24H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7200000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT24H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>69</UID>
            <ID>69</ID>
            <Name>Install adapter 2</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:39:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.3.2.1</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-30T08:00:00</Start>
            <Finish>2009-12-30T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7200000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>70</UID>
            <ID>70</ID>
            <Name>Configure adapter 2</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:39:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.3.2.2</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-31T08:00:00</Start>
            <Finish>2009-12-31T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7200000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>69</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>71</UID>
            <ID>71</ID>
            <Name>Review and approve adapter 2 installation</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:39:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.3.2.3</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7200000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>70</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>72</UID>
            <ID>72</ID>
            <Name>Configure Tivoli Identity Manager</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:39:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-30T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT24H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6720000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT24H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>73</UID>
            <ID>73</ID>
            <Name>Configure adapter forms</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:39:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.1</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-30T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT24H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6720000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT24H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>74</UID>
            <ID>74</ID>
            <Name>Configure adapter 1 form</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:39:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.1.1</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-30T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT24H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6720000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT24H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>75</UID>
            <ID>75</ID>
            <Name>Identify required variables</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:39:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.1.1.1</OutlineNumber>
            <OutlineLevel>7</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-30T08:00:00</Start>
            <Finish>2009-12-30T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6720000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>76</UID>
            <ID>76</ID>
            <Name>Modify standard forms</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:39:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.1.1.2</OutlineNumber>
            <OutlineLevel>7</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-31T08:00:00</Start>
            <Finish>2009-12-31T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6720000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>75</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>77</UID>
            <ID>77</ID>
            <Name>Obtain customer signoff on forms development</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:39:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.1.1.3</OutlineNumber>
            <OutlineLevel>7</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6720000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>76</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>78</UID>
            <ID>78</ID>
            <Name>Configure adapter 2 form</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:39:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.1.2</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-30T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT24H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6720000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT24H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>79</UID>
            <ID>79</ID>
            <Name>Identify required variables</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:40:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.1.2.1</OutlineNumber>
            <OutlineLevel>7</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-30T08:00:00</Start>
            <Finish>2009-12-30T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6720000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>80</UID>
            <ID>80</ID>
            <Name>Modify standard forms</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:40:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.1.2.2</OutlineNumber>
            <OutlineLevel>7</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-31T08:00:00</Start>
            <Finish>2009-12-31T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6720000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>79</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>81</UID>
            <ID>81</ID>
            <Name>Obtain customer signoff on forms development</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:40:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.1.2.3</OutlineNumber>
            <OutlineLevel>7</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6720000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>80</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>82</UID>
            <ID>82</ID>
            <Name>Configure organizational roles</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:40:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.2</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-31T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT16H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6240000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT16H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>83</UID>
            <ID>83</ID>
            <Name>Configure organizational roles</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:40:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.2.1</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-31T08:00:00</Start>
            <Finish>2009-12-31T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6240000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>84</UID>
            <ID>84</ID>
            <Name>Test organizational roles</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:40:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.2.2</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6240000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>83</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>85</UID>
            <ID>85</ID>
            <Name>Configure provisioning policies</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:40:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.3</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-30T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT24H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6720000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT24H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>86</UID>
            <ID>86</ID>
            <Name>Configure provisioning policies</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:40:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.3.1</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-30T08:00:00</Start>
            <Finish>2009-12-30T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6720000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>87</UID>
            <ID>87</ID>
            <Name>Configure Workflow</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T17:17:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.3.2</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-31T08:00:00</Start>
            <Finish>2009-12-31T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6720000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>86</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>88</UID>
            <ID>88</ID>
            <Name>Test provisioning policies and workflow</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:40:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.3.3</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6720000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>87</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>89</UID>
            <ID>89</ID>
            <Name>Configure Tivoli Identity Manager security (ACIs and groups)</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:40:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.4</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-31T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT16H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6240000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT16H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>90</UID>
            <ID>90</ID>
            <Name>Create ITIM groups</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:41:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.4.1</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5760000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>91</UID>
            <ID>91</ID>
            <Name>Configure Tivoli Identity Manager security (ACIs)</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:41:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.4.2</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-31T08:00:00</Start>
            <Finish>2009-12-31T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6240000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>92</UID>
            <ID>92</ID>
            <Name>Test Tivoli Identity Manager security (ACIs and groups)</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:41:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.4.3</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6240000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>91</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>93</UID>
            <ID>93</ID>
            <Name>Configure password policies</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:41:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.5</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-31T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT16H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6240000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT16H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>94</UID>
            <ID>94</ID>
            <Name>Configure password policies</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:41:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.5.1</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-31T08:00:00</Start>
            <Finish>2009-12-31T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6240000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>95</UID>
            <ID>95</ID>
            <Name>Test password policies</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:41:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.5.2</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6240000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>94</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>96</UID>
            <ID>96</ID>
            <Name>Configure identity policies</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:41:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.6</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-31T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT16H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6240000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT16H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>97</UID>
            <ID>97</ID>
            <Name>Configure identity policies</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:42:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.6.1</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-31T08:00:00</Start>
            <Finish>2009-12-31T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6240000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>98</UID>
            <ID>98</ID>
            <Name>Test identity policies</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:42:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.6.2</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6240000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>97</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>99</UID>
            <ID>99</ID>
            <Name>Review and approve Tivoli Identity Manager configuration</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:42:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.3.4.7</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T12:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT4H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5520000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT4H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>100</UID>
            <ID>100</ID>
            <Name>Develop data import methods</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:42:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-07T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT160H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7680000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT160H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>101</UID>
            <ID>101</ID>
            <Name>Full HR data load</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:42:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.1</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-07T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT160H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6720000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT160H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>102</UID>
            <ID>102</ID>
            <Name>Design data extraction method</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.1.1</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T12:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT4H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-5520000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT4H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>103</UID>
            <ID>103</ID>
            <Name>Obtain schema and file layout</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.1.2</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-07T08:00:00</Start>
            <Finish>2009-12-07T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14880000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>104</UID>
            <ID>104</ID>
            <Name>Get access to sample data</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.1.3</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-31T08:00:00</Start>
            <Finish>2009-12-31T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6720000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>103</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>105</UID>
            <ID>105</ID>
            <Name>Map data to Tivoli Identity Manager data</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.1.4</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6720000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>104</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>106</UID>
            <ID>106</ID>
            <Name>Get test file</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.1.5</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-08T08:00:00</Start>
            <Finish>2009-12-08T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14880000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>103</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>107</UID>
            <ID>107</ID>
            <Name>Load test data</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.1.6</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-09T08:00:00</Start>
            <Finish>2009-12-09T12:00:00</Finish>
            <Duration>PT4H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14880000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT4H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>106</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>108</UID>
            <ID>108</ID>
            <Name>Review results and approve</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.1.7</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T12:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT4H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6720000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT4H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>107</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>109</UID>
            <ID>109</ID>
            <Name>Incremental HR data load</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.2</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-28T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT40H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7680000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT40H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>110</UID>
            <ID>110</ID>
            <Name>Design data extraction method</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.2.1</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-28T08:00:00</Start>
            <Finish>2009-12-28T12:00:00</Finish>
            <Duration>PT4H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7680000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT4H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>111</UID>
            <ID>111</ID>
            <Name>Obtain schema and file layout</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.2.2</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-28T12:00:00</Start>
            <Finish>2009-12-29T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7680000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>110</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>112</UID>
            <ID>112</ID>
            <Name>Get access to sample data</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.2.3</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-31T08:00:00</Start>
            <Finish>2009-12-31T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6960000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>111</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>113</UID>
            <ID>113</ID>
            <Name>Code incremental load routines</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.2.4</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6960000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>112</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>114</UID>
            <ID>114</ID>
            <Name>Get test file</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.2.5</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-29T12:00:00</Start>
            <Finish>2009-12-30T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7680000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>111</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>115</UID>
            <ID>115</ID>
            <Name>Load test data</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.2.6</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-30T12:00:00</Start>
            <Finish>2009-12-31T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7680000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>114</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>116</UID>
            <ID>116</ID>
            <Name>Automate incremental load</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.2.7</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-31T12:00:00</Start>
            <Finish>2010-01-01T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7680000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>115</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>117</UID>
            <ID>117</ID>
            <Name>Review results and approve</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.2.8</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T12:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT4H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7680000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT4H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>116</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>118</UID>
            <ID>118</ID>
            <Name>Load and configure organization tree</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.3</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-28T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT40H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7680000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT40H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>119</UID>
            <ID>119</ID>
            <Name>Design extraction method</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.3.1</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-28T08:00:00</Start>
            <Finish>2009-12-28T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7680000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>120</UID>
            <ID>120</ID>
            <Name>Obtain schema and file layout</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.3.2</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-29T08:00:00</Start>
            <Finish>2009-12-29T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7680000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>119</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>121</UID>
            <ID>121</ID>
            <Name>Map data to Tivoli Identity Manager schema</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.3.3</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-30T08:00:00</Start>
            <Finish>2009-12-30T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7680000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>120</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>122</UID>
            <ID>122</ID>
            <Name>Get access to test data</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.3.4</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-31T08:00:00</Start>
            <Finish>2009-12-31T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7680000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>121</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>123</UID>
            <ID>123</ID>
            <Name>Execute test</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.3.5</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-7680000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>122</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>124</UID>
            <ID>124</ID>
            <Name>Review results and approve</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.3.6</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-30T08:00:00</Start>
            <Finish>2009-12-30T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6720000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>125</UID>
            <ID>125</ID>
            <Name>Load full set of organization chart info</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.3.7</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-31T08:00:00</Start>
            <Finish>2009-12-31T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6720000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>124</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>126</UID>
            <ID>126</ID>
            <Name>Review results and approve</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:43:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.4.3.8</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2010-01-01T08:00:00</Start>
            <Finish>2010-01-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-6720000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>125</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>127</UID>
            <ID>127</ID>
            <Name>Test overall Tivoli Identity Manager processes</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:44:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-09T12:00:00</Start>
            <Finish>2009-12-15T12:00:00</Finish>
            <Duration>PT32H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14880000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT32H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>107</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>128</UID>
            <ID>128</ID>
            <Name>Test Tivoli Identity Manager security policies</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:44:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.1</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-14T12:00:00</Start>
            <Finish>2009-12-15T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13440000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>129</UID>
            <ID>129</ID>
            <Name>Test proper access for Tivoli Identity Manager administrators</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:44:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.1.1</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-14T12:00:00</Start>
            <Finish>2009-12-15T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13440000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>130</UID>
            <ID>130</ID>
            <Name>Test proper exclusion from administrative tasks for non-administrators</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:44:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.1.1.1</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-14T12:00:00</Start>
            <Finish>2009-12-15T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13440000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>131</UID>
            <ID>131</ID>
            <Name>Test manual registration</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:44:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.2</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-09T12:00:00</Start>
            <Finish>2009-12-15T12:00:00</Finish>
            <Duration>PT32H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14880000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT32H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>132</UID>
            <ID>132</ID>
            <Name>Add user</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:45:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.2.1</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-09T12:00:00</Start>
            <Finish>2009-12-10T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14880000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>133</UID>
            <ID>133</ID>
            <Name>Delete user</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:45:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.2.2</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-10T12:00:00</Start>
            <Finish>2009-12-11T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14880000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>132</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>134</UID>
            <ID>134</ID>
            <Name>Transfer user between organizational units</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:45:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.2.3</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-11T12:00:00</Start>
            <Finish>2009-12-14T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14880000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>133</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>135</UID>
            <ID>135</ID>
            <Name>Test modification of user data</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:45:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.2.4</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-14T12:00:00</Start>
            <Finish>2009-12-15T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14880000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>134</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>136</UID>
            <ID>136</ID>
            <Name>Test provisioning policies (repeat for each policy)</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:45:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.3</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-14T12:00:00</Start>
            <Finish>2009-12-15T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13440000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>137</UID>
            <ID>137</ID>
            <Name>Test automatic provisioning on import from HR feed (repeat for each organization role)</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:45:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.3.1</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-14T12:00:00</Start>
            <Finish>2009-12-15T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13440000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>138</UID>
            <ID>138</ID>
            <Name>Test manual provisioning (repeat for each organization role)</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:45:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.3.2</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-14T12:00:00</Start>
            <Finish>2009-12-15T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13440000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>139</UID>
            <ID>139</ID>
            <Name>Test for exclusion based on organizational role</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:45:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.3.2.1</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-14T12:00:00</Start>
            <Finish>2009-12-15T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13440000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>140</UID>
            <ID>140</ID>
            <Name>Test for inclusion based on organizational role</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:45:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.3.2.2</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-14T12:00:00</Start>
            <Finish>2009-12-15T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13440000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>141</UID>
            <ID>141</ID>
            <Name>Test workflow</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:46:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.3.3</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-14T12:00:00</Start>
            <Finish>2009-12-15T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13440000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>142</UID>
            <ID>142</ID>
            <Name>Test approvals</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:46:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.3.3.1</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-14T12:00:00</Start>
            <Finish>2009-12-15T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13440000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>143</UID>
            <ID>143</ID>
            <Name>Test rejections</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:46:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.3.3.2</OutlineNumber>
            <OutlineLevel>6</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-14T12:00:00</Start>
            <Finish>2009-12-15T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13440000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>144</UID>
            <ID>144</ID>
            <Name>Test adapter (repeat for each adapter)</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:46:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.4</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-11T12:00:00</Start>
            <Finish>2009-12-15T12:00:00</Finish>
            <Duration>PT16H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13920000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT16H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>145</UID>
            <ID>145</ID>
            <Name>Add accesses</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:47:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.4.1</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-11T12:00:00</Start>
            <Finish>2009-12-14T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13920000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>146</UID>
            <ID>146</ID>
            <Name>Change accesses</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:47:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.4.2</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-11T12:00:00</Start>
            <Finish>2009-12-14T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13920000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>147</UID>
            <ID>147</ID>
            <Name>Suspend accesses</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:47:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.4.3</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-11T12:00:00</Start>
            <Finish>2009-12-14T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13920000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>148</UID>
            <ID>148</ID>
            <Name>Restore accesses</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:47:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.4.4</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-11T12:00:00</Start>
            <Finish>2009-12-14T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13920000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>149</UID>
            <ID>149</ID>
            <Name>Reset passwords</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:47:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.4.5</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-11T12:00:00</Start>
            <Finish>2009-12-14T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13920000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>150</UID>
            <ID>150</ID>
            <Name>Change passwords</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:47:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.4.6</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-11T12:00:00</Start>
            <Finish>2009-12-14T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13920000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>151</UID>
            <ID>151</ID>
            <Name>Delete accesses</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:47:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.4.7</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-11T12:00:00</Start>
            <Finish>2009-12-14T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13920000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>152</UID>
            <ID>152</ID>
            <Name>Run reconciliations</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:47:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.4.8</OutlineNumber>
            <OutlineLevel>5</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-14T12:00:00</Start>
            <Finish>2009-12-15T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13920000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>145</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <PredecessorLink>
                <PredecessorUID>146</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <PredecessorLink>
                <PredecessorUID>147</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <PredecessorLink>
                <PredecessorUID>148</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <PredecessorLink>
                <PredecessorUID>149</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <PredecessorLink>
                <PredecessorUID>150</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <PredecessorLink>
                <PredecessorUID>151</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>153</UID>
            <ID>153</ID>
            <Name>Setup and test reconciliation schedule</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:47:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.5</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-14T12:00:00</Start>
            <Finish>2009-12-15T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13440000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>154</UID>
            <ID>154</ID>
            <Name>Review and approve test results</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:47:00</CreateDate>
            <WBS/>
            <OutlineNumber>2.2.5.6</OutlineNumber>
            <OutlineLevel>4</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-14T12:00:00</Start>
            <Finish>2009-12-15T12:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-13440000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>156</UID>
            <ID>156</ID>
            <Name>Prepare production systems</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:47:00</CreateDate>
            <WBS/>
            <OutlineNumber>4</OutlineNumber>
            <OutlineLevel>1</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-11-30T08:00:00</Start>
            <Finish>2009-12-22T17:00:00</Finish>
            <Duration>PT136H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-14880000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT136H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>157</UID>
            <ID>157</ID>
            <Name>Train Tivoli Identity Manager administrator</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:47:00</CreateDate>
            <WBS/>
            <OutlineNumber>4.1</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-22T08:00:00</Start>
            <Finish>2009-12-22T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-4320000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>158</UID>
            <ID>158</ID>
            <Name>Ensure hardware is available</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:47:00</CreateDate>
            <WBS/>
            <OutlineNumber>4.2</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-11-30T08:00:00</Start>
            <Finish>2009-11-30T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-12000000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>159</UID>
            <ID>159</ID>
            <Name>Configure hardware</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:47:00</CreateDate>
            <WBS/>
            <OutlineNumber>4.3</OutlineNumber>
            <OutlineLevel>2</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-01T08:00:00</Start>
            <Finish>2009-12-03T17:00:00</Finish>
            <Duration>PT24H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-12000000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT24H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>158</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>160</UID>
            <ID>160</ID>
            <Name>Receive and inventory hardware</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:47:00</CreateDate>
            <WBS/>
            <OutlineNumber>4.3.1</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-01T08:00:00</Start>
            <Finish>2009-12-01T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-12000000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>161</UID>
            <ID>161</ID>
            <Name>Install hardware</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:47:00</CreateDate>
            <WBS/>
            <OutlineNumber>4.3.2</OutlineNumber>
            <OutlineLevel>3</OutlineLevel>
            <Priority>500</Priority>
            <Start>2009-12-02T08:00:00</Start>
            <Finish>2009-12-02T17:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <Work>PT0H0M0S</Work>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>1</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>1</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <StartVariance>0</StartVariance>
            <FinishVariance>0</FinishVariance>
            <WorkVariance>0</WorkVariance>
            <FreeSlack>0</FreeSlack>
            <TotalSlack>-12000000</TotalSlack>
            <FixedCost>0</FixedCost>
            <FixedCostAccrual>2</FixedCostAccrual>
            <Cost>0</Cost>
            <OvertimeCost>0</OvertimeCost>
            <OvertimeWork>PT0H0M0S</OvertimeWork>
            <ActualDuration>PT0H0M0S</ActualDuration>
            <ActualCost>0</ActualCost>
            <ActualOvertimeCost>0</ActualOvertimeCost>
            <ActualWork>PT0H0M0S</ActualWork>
            <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
            <RegularWork>PT0H0M0S</RegularWork>
            <RemainingDuration>PT8H0M0S</RemainingDuration>
            <RemainingCost>0</RemainingCost>
            <RemainingWork>PT0H0M0S</RemainingWork>
            <RemainingOvertimeCost>0</RemainingOvertimeCost>
            <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
            <ACWP>0</ACWP>
            <CV>0</CV>
            <ConstraintType>1</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>1970-01-01T00:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <LevelingDelay>0</LevelingDelay>
            <LevelingDelayFormat>5</LevelingDelayFormat>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes/>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <BCWS>0</BCWS>
            <BCWP>0</BCWP>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>160</PredecessorUID>
                <Type>1</Type>
            </PredecessorLink>
            <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
            <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
            <UID>162</UID>
            <ID>162</ID>
            <Name>Execute manufacture’s check list</Name>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <CreateDate>2010-06-28T16:47:00</Cr